J
JamesG
Two questions
1. i have set up an admin project using the help to allow our team to
allocate holiday etc, however following the example in the help i now have
sent the team a vacation. I thought i was just setting them up so they could
enter their holiday into project server so that they were not allocated to
tasks during their holiday. could someone please explain how this works
2. I have been asked by my boss to set this up so that we can allocate cost
centers to various projects for billing purposes. Is there a well documented
way of doing this? i was thinking about usng custom fields, but would like to
know if there's a better option
thanks in advance
James
1. i have set up an admin project using the help to allow our team to
allocate holiday etc, however following the example in the help i now have
sent the team a vacation. I thought i was just setting them up so they could
enter their holiday into project server so that they were not allocated to
tasks during their holiday. could someone please explain how this works
2. I have been asked by my boss to set this up so that we can allocate cost
centers to various projects for billing purposes. Is there a well documented
way of doing this? i was thinking about usng custom fields, but would like to
know if there's a better option
thanks in advance
James