I have created 2 Admin projects in Project Server 2003. These admin projects
however are showing up in the regular project pool and are also (I think)
causing my resources to be overallocated. When resources submit their
timesheets the admin hours are being counted and Project is adjusting
durations on admin projects when it shouldn't. There shouldn't be any
durations for admin projects, should there? I want to make sure that the
resource allocations are correct before I make adjustments to resource time.