Admin Time handling and Reporting

L

laguna

I need to create a report displaying status of the Administrative Time for
the managers to keep track of admin time already approved or pending.
Administrative Time can be approved while Timesheet is
in the future and waiting for approval. How can I separate these two
(Timesheet and Admin Time Off) for the reporting purposes? What field in the
database gets
updated when manager approves Admin time request? And what is the
Enterprise Resource Pool where this approved Time Off is reflected? How can I
see it?
 
G

Gary L. Chefetz

laguna:

As Dale states, you're asking developer questions but you're not addressing
them to the correct newsgroup. If you want to get into developing against
Project Server, we have a complete list of resources here:

http://www.projectserverexperts.com/Lists/Project Developer Resources/Resources.aspx

These links will point you toward important resources. You need to download
the SDK immediately along with an SSRS report starter package, which you can
use to get started. Some of your requirements are addressed in these
pre-built reports here:

http://blogs.msdn.com/chrisfie/arch...nded-report-pack-from-project-conference.aspx
 