B
Bob Schroen
I have an Administrative project that has recorded a value of 780 hours for
vacation time for one resource, but the actual work (from MSP_WEB_WORK)
shows only a total of 60 hours the difference of 720 hours was adjusted by
the option "Adjust Actuals"
The time sheet summary is correct but the porfolio analyzer and the "Actual
Work" and "Actual Work Protected" via the MS Project Pro is not correct.
This leeds to the question where is this information stored and how can I
fix it.
Thanks in advance - Bob
vacation time for one resource, but the actual work (from MSP_WEB_WORK)
shows only a total of 60 hours the difference of 720 hours was adjusted by
the option "Adjust Actuals"
The time sheet summary is correct but the porfolio analyzer and the "Actual
Work" and "Actual Work Protected" via the MS Project Pro is not correct.
This leeds to the question where is this information stored and how can I
fix it.
Thanks in advance - Bob