***For Project 2003 Only***

Project '03 doesn't change resource calendars from
administrative file updates. Project treats vacation and
other non-project time as high-priority tasks (priority =
1000). I've found that entering only duration in
administrative files doesn't change resource
availability. Instead, I enter work and this updates
resource availability! Also, don't forget to publish the
updates in the administrative file. If you don't publish
this info, it won't be available when you try to level
based on the decreased availability.