Administrative project - import timesheets

X

XTOF70

I decided te create an project that contains all of our administrative tasks,
instead of the "administrative time" feature.
I created an mpp with all activities, all employees and assigned all
employees to these activities in order to have them appearing in "My
timesheet".
I used fix duration, not effort driven and 0 work for each assignment. This
iploies that duration is set to 0 too.
I succeed selecting the correct activities in "My timesheet", the planned =
0, but I can enter and submit this timeheet after entering the actuals.

I'm not able to import these actuals to the task via "My task". what am i
doing wrong ? A setting on project server of wrong mpp setting ?

Thx
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top