administrative project in project 03

J

Jimbo

hi

i have resources assigned to an administrative project in
project server 2003. when they schedule themselves for
vacation, everything works perfectly. the problem is
that when i level projects with these resources, it
doesnt take the scheduled vacation into account - even
though its scheduled with priority 1000. why!!! this is
driving me nuts! will updating the OLAP cube handle this
problem?

a million thanks
 
S

Sean

Jimbo:

To make sure that resources level against all booked
time, open all files in which they are assigned and
consolidate them temporarily. This way you won't have to
figure out all of Project's leveling quirks.

Hope this helps!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top