Renee IT/PM
We use an Administrative Project to track non-project and non-working time.
I'm using the book "Administering an enterprise PMO", page 242 as a
reference tool.
I have added two new employees to the Administrative project as Resources.
I have three issues:
1) On the Resource tab
There are several Resources that have a "message" of
"This resource should be level based on a Day by Day setting".
The two new resources have the message - but so do many others.
What does that mean and what should I do (if anything)?
2) On the Tasks tab
There are three tasks and in the Resource Names column the new resources are
listed.
But when I clicked on the cell dropdown arrow to verify the names - this
message occurs.
The resource list is too long.
A resource list that contains more than 256 characters cannot be edited or
deleted or used on the To line of a message.
use the Resource Information dialog box to edit long resource names.
<OK>
What is a "Resource Information dialog box"?
At this point the tabs (Tasks, Resrouces, et al) and the menu items
(File>Save et al) are disabled so I can not republish the project.
I have End the Task using Windows Task manager and then Check in the project
using PWA.
3) The new employees (resources) get this message when they want to enter
non-working time.
"You are not assigned to any tasks on any administrative project, such as
vacation, sick, or bereavement.
To submit time against an administrative project, you must be assigned to a
task on that project for the time period that you are unavailable for project
work.
Contact your server administrator if you feel you have received this message
in error. "
I'm using the book "Administering an enterprise PMO", page 242 as a
reference tool.
I have added two new employees to the Administrative project as Resources.
I have three issues:
1) On the Resource tab
There are several Resources that have a "message" of
"This resource should be level based on a Day by Day setting".
The two new resources have the message - but so do many others.
What does that mean and what should I do (if anything)?
2) On the Tasks tab
There are three tasks and in the Resource Names column the new resources are
listed.
But when I clicked on the cell dropdown arrow to verify the names - this
message occurs.
The resource list is too long.
A resource list that contains more than 256 characters cannot be edited or
deleted or used on the To line of a message.
use the Resource Information dialog box to edit long resource names.
<OK>
What is a "Resource Information dialog box"?
At this point the tabs (Tasks, Resrouces, et al) and the menu items
(File>Save et al) are disabled so I can not republish the project.
I have End the Task using Windows Task manager and then Check in the project
using PWA.
3) The new employees (resources) get this message when they want to enter
non-working time.
"You are not assigned to any tasks on any administrative project, such as
vacation, sick, or bereavement.
To submit time against an administrative project, you must be assigned to a
task on that project for the time period that you are unavailable for project
work.
Contact your server administrator if you feel you have received this message
in error. "