B
Brian
We've been testing the use of admin projects in PWA. We use PWA 2003, SP1.
When a resource submits some time to the administrative plan, we don't see
that the resource manager is getting notified of the submission. Is there a
permission that must be enabled?
Thanks,
Brian
When a resource submits some time to the administrative plan, we don't see
that the resource manager is getting notified of the submission. Is there a
permission that must be enabled?
Thanks,
Brian