I
Ivor Davies
Just a general query to gauge a consensus on how to properly setup an
administrative time project in EPM.
My manager wishes to create a project that spans from April 1st 2006 to
March 31 2007 to track our department's administrative time such as vacation,
meetings, time out of the office, etc..
Is the proper convention using the administrative time template to setup the
project as follows:
1) Start Date = April 1st 2006
2) End Date = March 31st 2007
3) Task Type = Fixed Duration
4) Not Effort Driven
5) Constraint Type = Finish no earlier than March 31st 2007
6) Duration = 248 Days
When assigning resources to this task should the UNITs be 100%?
Should the Earned Value Method be Physical % Complete OR % Complete?
How have others setup these projects?
I want to ensure that my manager can ACURATELY REPORT on the ACUTAL WORK for
each resource in our department.
Any assistance or response would be greatly appreciated.
Thank You.
Ivor
administrative time project in EPM.
My manager wishes to create a project that spans from April 1st 2006 to
March 31 2007 to track our department's administrative time such as vacation,
meetings, time out of the office, etc..
Is the proper convention using the administrative time template to setup the
project as follows:
1) Start Date = April 1st 2006
2) End Date = March 31st 2007
3) Task Type = Fixed Duration
4) Not Effort Driven
5) Constraint Type = Finish no earlier than March 31st 2007
6) Duration = 248 Days
When assigning resources to this task should the UNITs be 100%?
Should the Earned Value Method be Physical % Complete OR % Complete?
How have others setup these projects?
I want to ensure that my manager can ACURATELY REPORT on the ACUTAL WORK for
each resource in our department.
Any assistance or response would be greatly appreciated.
Thank You.
Ivor