R
Rachel
I'm using Project Server 2007. I have a few questions about administrative
time.
1) Using all the administrative tasks (i.e. sick leave, jury duty, vacation,
staff meetings) our company uses will make the timesheets in PWA very tall.
As a workaround, does it make sense to create a seperate Administrative
Project with administrative tasks that every resource is assigned to with 0
hours? Then, when a resource takes a vacation day they can report hours
against the task on their timesheet? I also want resources to submit vacation
requests through PWA. Will managing admin time through a seperate project get
in the way of doing this?
2) Are their timesheet reports that I can configure? I'm asking because I
don't want all the tasks resources are reporting against to show on the
timesheets we submit to our payroll coordinator. I would like all tasks
(exclusive of administrative time) to roll up to the row 0 summary task in
the timesheet report. Is this possible?
Thanks,
Rachel
time.
1) Using all the administrative tasks (i.e. sick leave, jury duty, vacation,
staff meetings) our company uses will make the timesheets in PWA very tall.
As a workaround, does it make sense to create a seperate Administrative
Project with administrative tasks that every resource is assigned to with 0
hours? Then, when a resource takes a vacation day they can report hours
against the task on their timesheet? I also want resources to submit vacation
requests through PWA. Will managing admin time through a seperate project get
in the way of doing this?
2) Are their timesheet reports that I can configure? I'm asking because I
don't want all the tasks resources are reporting against to show on the
timesheets we submit to our payroll coordinator. I would like all tasks
(exclusive of administrative time) to roll up to the row 0 summary task in
the timesheet report. Is this possible?
Thanks,
Rachel