Administrative Recurring Tasks

A

Al

When enterting time via Resources: Adjust Actuals for recurring tasks (team
meetings, etc.) the hours entered are showing as actuals for the person
adjusting the hours.

Example:
The project managers have to enter time for business resources and external
vendors. When entering time for a recurring task the actual hours are
appearing in the project manager's timesheet as actual work. Is there a
problem with recurring task in Managed Time Periods?

Thanks
 