Administrative tasks / calendar

S

S. Persoon

I have a customer that uses PWA for resourceplanning at a task level. They do
not use the time-writing feature, because they have a separate system for
that. They use the the following information for planning resources in
projects.

1. workweek is 36 hrs
2. 80% of 36 hrs the resource are productive (so the orher 20% they are sick
or go to the toilet etc.)
3. beside this percentage resources have a maximum percentage of units they
are available for working in projects (for instant 20%)

I would like to know if anybody has an idea how to configure this the best
way for the customer. I read al lot about Admin-projects etc. but I can not
find a suitable answer so far.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top