administrative tasks timesheet is not importing into my tasks page

S

Sam

we are new in epm 2007 environment

in which one team member enter some hours into one administrative tasks and
after approved from his timesheet manager when try to import into my tasks
page in the import dialog box . when he is selecting a specific timesheet the
tasks of this timesheet are not displaying bottom and when he try to click on
import button nothing is happen.

pls tell me the solution or issue. why this is happening.
 
M

Marc Soester [MVP]

HI Sam,

this is no issue, but by design. An administrative task is not a project
task and it therefore cannot be imported into the my task page.
Hope this helps
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top