R
RK
We just installed the Project server and are using Admin projects to track
our general time on operational issues. Every time a user enters time
against one of these tasks and it is updated and approved, the remaining time
goes up, the project dates change and an email is sent to all users assigned
to the task.
For example, if a user enters 4 hrs against Sick Days, in PWA and the
approval screen, everything looks fine. As the PM, I accept the changes and
update. After the system automatically opens up project to update the actual
plan, it changes the dates for the task and sends an email to ALL users
assigned to it. The next time I go into the PWA, the user can see that task
with 4 hours of their time, but they also see that 4 hours are now remaining
on the task.
Is something set up wrong in the admin project?
our general time on operational issues. Every time a user enters time
against one of these tasks and it is updated and approved, the remaining time
goes up, the project dates change and an email is sent to all users assigned
to the task.
For example, if a user enters 4 hrs against Sick Days, in PWA and the
approval screen, everything looks fine. As the PM, I accept the changes and
update. After the system automatically opens up project to update the actual
plan, it changes the dates for the task and sends an email to ALL users
assigned to it. The next time I go into the PWA, the user can see that task
with 4 hours of their time, but they also see that 4 hours are now remaining
on the task.
Is something set up wrong in the admin project?