I
Irish Gues
A couple of questions on Administrative Projects...
1. I created 4 new tasks in my admin project - work orders, out of office,
administrative, maintenance. I didn't change any work, duration or dates as
instructed. I then added my resources and published the project. Now, every
time someone updates their time and I go in to accept their time, an email is
sent to the whole group saying that their tasks have changed. How do I fix
this????
2. We just rolled out EPM in my department and I have only had two people
enter in time against a couple of my adminstrative tasks, yet they are
showing as completed now. How do I fix this?
Thank you in advance!!!
1. I created 4 new tasks in my admin project - work orders, out of office,
administrative, maintenance. I didn't change any work, duration or dates as
instructed. I then added my resources and published the project. Now, every
time someone updates their time and I go in to accept their time, an email is
sent to the whole group saying that their tasks have changed. How do I fix
this????
2. We just rolled out EPM in my department and I have only had two people
enter in time against a couple of my adminstrative tasks, yet they are
showing as completed now. How do I fix this?
Thank you in advance!!!