Sheri
Using PS 2007
We have been using Administrative Time for about 1 month with no problem.
Starting yesterday (to the best of my knowledge) here is the problem:
Team member uses the Plan Administrative Time and placed some hours in the
Planned row of Vacation. The Admin Time does go to the Timesheet manager and
the Timesheet Manager approves it.
Team member goes to the timesheet enters Actuals for that planned time (that
appears as a green dot because it was approved). They are not ready to
submit, so they just hit Save on their Timesheet.
The system changes the dot to yellow. Now they cannot submit until it gets
approved AGAIN....any time Recalculate or Save is hit, it requires the Admin
Time to be approved again.
HELP!!!!
We have been using Administrative Time for about 1 month with no problem.
Starting yesterday (to the best of my knowledge) here is the problem:
Team member uses the Plan Administrative Time and placed some hours in the
Planned row of Vacation. The Admin Time does go to the Timesheet manager and
the Timesheet Manager approves it.
Team member goes to the timesheet enters Actuals for that planned time (that
appears as a green dot because it was approved). They are not ready to
submit, so they just hit Save on their Timesheet.
The system changes the dot to yellow. Now they cannot submit until it gets
approved AGAIN....any time Recalculate or Save is hit, it requires the Admin
Time to be approved again.
HELP!!!!