Administrative Time Details View

S

Sebastian Cordoba

Hello Everyone.

I need to know if there's a way to visualize the administrative time reports
details for a specific resource. I know we can use the Resource Availability
option to see the TOTAL amount of hours reported by a resource in his
timesheets, but we need to know the details, I mean, the amount of hours
reported for each category of administrative time. This is an example:
Resource R1
My Timesheets
Period X (Date 1 - Date 2)
Mail Reading 4h
Meetings 6h
...

It would be nice If we could add this information to the Resource
Assignments view, so that we can have both the infomation about project tasks
and administrative time, for the selected resource.


So, what can I do? Thanks for your help.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top