Administrative Time MS Project 2007

M

Manish

We want to use Administrative time feature in 2007. But we want to avoid
using Timesheets. We want Admin time categories such as Vacation, Training
etc should show up in the My tasks view itself. Is there a way to achieve
that without using the Import timesheet fucntion and Administrative projects
like we used to do in 2003?
 
J

Jonathan Sofer

There is no "Administrative" type project in 2007 but you can use a normal
project and add task activities like Vacation, Training, etc and assign all
your resources to it. The resource will update this via "My Tasks" and can
ignore "My Timesheets".
 