P
Proj_Admin
Hi,
The default method in my organization for reporting progress on tasks in
Project Web Access is set to:
• Hours of work done per day or per week
However, no Admin is able to adjust actuals. The resource tasks show up but
the boxes to enter either actual work or % complete are un-editable. I’ve
verified we have the permissions to Adjust Actuals. For security purposes,
we do not want various managers opening Microsoft Project, entering %
complete updates and republishing assignments. (Although I know it can be
done this way)
How can I enable admins (myself included) to adjust actuals?
Thanks,
Proj_Admin
The default method in my organization for reporting progress on tasks in
Project Web Access is set to:
• Hours of work done per day or per week
However, no Admin is able to adjust actuals. The resource tasks show up but
the boxes to enter either actual work or % complete are un-editable. I’ve
verified we have the permissions to Adjust Actuals. For security purposes,
we do not want various managers opening Microsoft Project, entering %
complete updates and republishing assignments. (Although I know it can be
done this way)
How can I enable admins (myself included) to adjust actuals?
Thanks,
Proj_Admin