amir d
hello,
few questions regarding the subject:
1. how do you remove a resource from one project and assigns him to another,
without removing/deleting his actual work (when you try to remove him,
project alerts that this resource has actuals and your'e about to delete it) ?
2. in several projects, when project managers / PMO accept updates from
resources and the project file is opened, more standard calendars are added
to the project (it should have only 3 calendars, one is used) - it alerts
that it's anout to add project calendars and afterwards you can see it in
tools >> organizer (standard111, standard 1325 and ct. ....). what could
cause this problem ?
3. there are some projects that has deadlines (relevant to milestones), but
the work is unknown (such as engineering documents and ct.). is it posssible
to use adminstrative projects somehow, so it'll have a "bucket" of hours, and
milestones - instead of using 2 projects ?
few questions regarding the subject:
1. how do you remove a resource from one project and assigns him to another,
without removing/deleting his actual work (when you try to remove him,
project alerts that this resource has actuals and your'e about to delete it) ?
2. in several projects, when project managers / PMO accept updates from
resources and the project file is opened, more standard calendars are added
to the project (it should have only 3 calendars, one is used) - it alerts
that it's anout to add project calendars and afterwards you can see it in
tools >> organizer (standard111, standard 1325 and ct. ....). what could
cause this problem ?
3. there are some projects that has deadlines (relevant to milestones), but
the work is unknown (such as engineering documents and ct.). is it posssible
to use adminstrative projects somehow, so it'll have a "bucket" of hours, and
milestones - instead of using 2 projects ?