J
Joe
Does the following scenario affect the SPI in a negative way?
Suppose someone works on a task and completes it. The task is now marked
100% complete. About a week later there is some additional re-work needed.
The person tracks his actuals to the same task. The task is still 100%
complete.
I understand that the CPI would be impacted negatively because there is now
more cost incurred. What about the SPI? Has the finish date changed,
thereby affecting the SPI too?
Suppose someone works on a task and completes it. The task is now marked
100% complete. About a week later there is some additional re-work needed.
The person tracks his actuals to the same task. The task is still 100%
complete.
I understand that the CPI would be impacted negatively because there is now
more cost incurred. What about the SPI? Has the finish date changed,
thereby affecting the SPI too?