After sorting & renumbering Project tasks they revert to old IDs

P

Pete in Dublin

After sorting and permanently renumbering Project tasks they initially look
fine, but when I save it and open the file again it has reverted to old ID
numbers.
 
J

Jim Aksel

I cannot duplicate here on Project Professional 2003, 2007, 2010. Please
verify you have all the latest service packs installed, etc.

If this does not correct the issue, please post back and state what version
you are running including service packs.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top