Is it possible to have a Custom Field on Project Level that is an aggregate
function of task properties (e.g. minimum task duration)?

Cheers,
Wouter
 
S

Sean Hanson

Yes, within defining a task custom field, you can set the Calculation for
Summary Rows, choose Rollup, then Aver, Min, Max, etc.
--
Sean Hanson

http://www.randsmanagement.com