You are correct - it does not warn you IF your designate the deadline
with a Finish No Later Than constraint - that's why I maintain so
strongly that constraints are not there to be used to force the schedule
to conform to the project's objectives and your use of this constraint
is incorrect. There is another field in the task information form in
Project 2000 or later labeled "Deadline" and that is exactly what it is
there for. If you specify the deadline date in that field and remove
the constraint, if conditions force the task to be delayed past the
deadline date Project will indeed red-flag it for you. BUT in no case
does it compare the scheduled date with the current date. You have to
have some condition - a predecessor that is late and posting its actual
forces the dependent tasks into the future or running the Reschedule
Uncompleted Work After ... tool moves the tasks in the schedule into the
future - to move the task in the Gantt chart to show it is now falling
after the deadline.
--
Steve House
MS Project MVP
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
confused said:
So basically what you're saying is that Project will not display any
type of warning if I am coming up on a dead line, and no work has been
done on the given task.