N
Nurazhar
Hi all,
I tried to look for a similar problem in the NG, but can't seem to find one,
so here goes.
Let's say I have a Task A (fixed duration) which runs from week 1 to week 3,
Task B (fixed duration) from week 2 to week 4, and the project finish date
is week 5. Is it possible to move the finish date to week 6, while Task A
and B keep their respective finish dates relative to the new finish date
(e.g: project finish date is week 6, Task A runs from week 2 to week 4, Task
B runs from week 3 to week 5). I will only be changing the project finish
date.
I have tried the 'Adjust Dates', but it doesn't seem to work well. With
reference to my comment in oisinirish's "Change Start date for project and
move all dependent tasks as wel", if the date entered is the same as the
current project finish date, all tasks will move back a day, and if the day
entered is one day after the current project finish date, the tasks will not
move.
This issue has me perplexed for like 2 days now, and I have exhausted all
searches online. I could be looking for the wrong thing, so I need your
help. =D
I look forward to your favourable reply. Thanks in advance!
Sincerely,
Nurazhar
I tried to look for a similar problem in the NG, but can't seem to find one,
so here goes.
Let's say I have a Task A (fixed duration) which runs from week 1 to week 3,
Task B (fixed duration) from week 2 to week 4, and the project finish date
is week 5. Is it possible to move the finish date to week 6, while Task A
and B keep their respective finish dates relative to the new finish date
(e.g: project finish date is week 6, Task A runs from week 2 to week 4, Task
B runs from week 3 to week 5). I will only be changing the project finish
date.
I have tried the 'Adjust Dates', but it doesn't seem to work well. With
reference to my comment in oisinirish's "Change Start date for project and
move all dependent tasks as wel", if the date entered is the same as the
current project finish date, all tasks will move back a day, and if the day
entered is one day after the current project finish date, the tasks will not
move.
This issue has me perplexed for like 2 days now, and I have exhausted all
searches online. I could be looking for the wrong thing, so I need your
help. =D
I look forward to your favourable reply. Thanks in advance!
Sincerely,
Nurazhar