Hello,
I created a Data Analysis view (on the MSP_Portfolio_Analyser cube) with the
3 "capacities":
- Base capacity
- Capacity
- Temporary Capacity (I still don't know what it means!)
I introduced some non working days in the enterprise calendar.
I introduced some vancancies in some resource calendars.
I increased the date range of the cube calculation
I ran the Cube calculation.

In the Data Analysis view, for each resource, these 3 capacity values are
the same !!!
What did I miss ?
Thanks for your help
 
R

Rod Gill

Did you re-publish the projects affected by the calendar changes? If not,
try that.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Robert said:
Hello,
I created a Data Analysis view (on the MSP_Portfolio_Analyser cube) with
the 3 "capacities":
- Base capacity
- Capacity
- Temporary Capacity (I still don't know what it means!)
I introduced some non working days in the enterprise calendar.
I introduced some vancancies in some resource calendars.
I increased the date range of the cube calculation
I ran the Cube calculation.

In the Data Analysis view, for each resource, these 3 capacity values are
the same !!!
What did I miss ?
Thanks for your help






__________ Information from ESET Smart Security, version of virus
signature database 4869 (20100215) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4869 (20100215) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top