Hi All
I have a software development project running for a number of months, but the detail and individual tasks are high in quantity. Therefore I do not want to have to manually allocate resources on a task by task basis
Due to the resources joining the team at different times I simply to create a 'Developer' group which is made up of 3 resources and just assign the group to every development task. For each individual I have amended their calendar accordingly, so I want MSP to work out when and who can work on each task
Due to the 3 resources having different calendars I cannot simply create a Developer resource and change max capacity to 300%
Thanks in advance for any help offered
I have a software development project running for a number of months, but the detail and individual tasks are high in quantity. Therefore I do not want to have to manually allocate resources on a task by task basis
Due to the resources joining the team at different times I simply to create a 'Developer' group which is made up of 3 resources and just assign the group to every development task. For each individual I have amended their calendar accordingly, so I want MSP to work out when and who can work on each task
Due to the 3 resources having different calendars I cannot simply create a Developer resource and change max capacity to 300%
Thanks in advance for any help offered