Allocatind Resources using groups

Joined
Jul 26, 2013
Messages
1
Reaction score
0
Hi All

I have a software development project running for a number of months, but the detail and individual tasks are high in quantity. Therefore I do not want to have to manually allocate resources on a task by task basis

Due to the resources joining the team at different times I simply to create a 'Developer' group which is made up of 3 resources and just assign the group to every development task. For each individual I have amended their calendar accordingly, so I want MSP to work out when and who can work on each task

Due to the 3 resources having different calendars I cannot simply create a Developer resource and change max capacity to 300%

Thanks in advance for any help offered
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top