D
Dee
Hello,
I've been using Project Server 2003 for a few months, but haven't yet
figured out the best way to allocate resources. Maybe some of you on
this group have some suggestions or would like to share your
experiences.
I realize that Project does not let you assign a resource at project
level. i.e you cannot assign a resource 40% on Project A 30% on Project
B and 30% on Project C. It has to be done at task level.
So now, if my resources have n number of tasks on Project A, I assign
40% on each task. But, my resources jump tasks, work on multiple tasks
at the same time. How do I handle assignming allocations in such
situations?
1) Levelling across multiple projects require opening each project. But
Project A, B and C are owned by different PMs.
2) Linking each resources tasks so that they fall one after the other
and the resource is not overallocated creates fake dependancies /
constraints. Every time I reschedule unfinished work, Project says it
could not reschedule certain tasks because of a constraint etc.
What is the best way of handling this. Will appreaciate any help.
TIA
Regards,
Dee
I've been using Project Server 2003 for a few months, but haven't yet
figured out the best way to allocate resources. Maybe some of you on
this group have some suggestions or would like to share your
experiences.
I realize that Project does not let you assign a resource at project
level. i.e you cannot assign a resource 40% on Project A 30% on Project
B and 30% on Project C. It has to be done at task level.
So now, if my resources have n number of tasks on Project A, I assign
40% on each task. But, my resources jump tasks, work on multiple tasks
at the same time. How do I handle assignming allocations in such
situations?
1) Levelling across multiple projects require opening each project. But
Project A, B and C are owned by different PMs.
2) Linking each resources tasks so that they fall one after the other
and the resource is not overallocated creates fake dependancies /
constraints. Every time I reschedule unfinished work, Project says it
could not reschedule certain tasks because of a constraint etc.
What is the best way of handling this. Will appreaciate any help.
TIA
Regards,
Dee