L
Lindsay
I have a 3,700 activity schedule with resources assigned. The resource are
groups, Examples: Elec, Piping, Welding. Each group has 10 men so I set the
max. units to 1000%. Now I need to allocate the units to the activity. Is
there any way to import this information from Excel? Right now when I click
on an activity the allocated units is 100% but I need to adjust them and I
don't want to have to click on all 3,700 activitys to do this.
groups, Examples: Elec, Piping, Welding. Each group has 10 men so I set the
max. units to 1000%. Now I need to allocate the units to the activity. Is
there any way to import this information from Excel? Right now when I click
on an activity the allocated units is 100% but I need to adjust them and I
don't want to have to click on all 3,700 activitys to do this.