Frank
Hello,
I am trying to allocate generic resources from the server, in my case sub
contractors. I am working on the 2007 versions of Project and server.
My problem is that i can't find a way to limit how many of these sub
contractors work on each project at any one time, meaning they all work on
one project and delay a later starting project until they're finished with
the first project, wheras in reality only a fraction work on each project.
A very simplified example would be that we have 10 sub contracted
bricklayers, I want 6 to work on one project and 4 to work on another.
Currently i am making a new generic resource for each project, ie "Bricklayer
1" and setting its max units to 600% & "Bricklayer 2" set at 400%.
My problem with this is that we have a lot of projects running in parallel
and a large pool of sub contractors. Is there a way to limit the amount of
resources available to our company from the sub contractor (in this case 10)
and then to be able to limit how many are available in each individual
project (in this case 6 and 4)?
Any help would be much apreciated
I am trying to allocate generic resources from the server, in my case sub
contractors. I am working on the 2007 versions of Project and server.
My problem is that i can't find a way to limit how many of these sub
contractors work on each project at any one time, meaning they all work on
one project and delay a later starting project until they're finished with
the first project, wheras in reality only a fraction work on each project.
A very simplified example would be that we have 10 sub contracted
bricklayers, I want 6 to work on one project and 4 to work on another.
Currently i am making a new generic resource for each project, ie "Bricklayer
1" and setting its max units to 600% & "Bricklayer 2" set at 400%.
My problem with this is that we have a lot of projects running in parallel
and a large pool of sub contractors. Is there a way to limit the amount of
resources available to our company from the sub contractor (in this case 10)
and then to be able to limit how many are available in each individual
project (in this case 6 and 4)?
Any help would be much apreciated