W
Wade
I have what I consider to be a basic project. The resources (they are
people) are set-up permanently at either 75% or 88%. The project is set-up
to use automatic leveling and everything is fixed units and effort driven. I
think everything else is set to default values. Evrything works fine except
one thing. When I assign a resource to a task that has less than 7 hours on
it the allocation for the resource is automatically lowered to match the
percentage of time it would take to complete the task. For example, when I
assign a resource to a task that has work of 2 hours, it changes the resource
to 25%. If I then reselect that same resource, the 75% or 88% shows back up
again. Any ideas why this happens? I have tried messing with various
options including the effort driven option and it always does the same thing
(changes my resource allocation the first time it is assigned). I am using
Project 2003.
people) are set-up permanently at either 75% or 88%. The project is set-up
to use automatic leveling and everything is fixed units and effort driven. I
think everything else is set to default values. Evrything works fine except
one thing. When I assign a resource to a task that has less than 7 hours on
it the allocation for the resource is automatically lowered to match the
percentage of time it would take to complete the task. For example, when I
assign a resource to a task that has work of 2 hours, it changes the resource
to 25%. If I then reselect that same resource, the 75% or 88% shows back up
again. Any ideas why this happens? I have tried messing with various
options including the effort driven option and it always does the same thing
(changes my resource allocation the first time it is assigned). I am using
Project 2003.