% allocation

A

assaf1978

Hi,
I have an activity in which a resource is 20% allocated on the first week,
80% on the second week and 100% on the last week.
Is there an option to create this task without splitting the it into 3
different ones?

Thanks,
Assaf
 
J

John

assaf1978 said:
Hi,
I have an activity in which a resource is 20% allocated on the first week,
80% on the second week and 100% on the last week.
Is there an option to create this task without splitting the it into 3
different ones?

Thanks,
Assaf

Assaf,
Sure, use the Resource Usage view to manually set the work hours for
that resource each week.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top