B
Ben Goldberg
I have a section in my plan called PRODUCTION SUPPORT and
under it several tasks like MEETINGS, PHONE CALLS, Etc..
Each resource is assigned to these tasks at 5%, but for
some reason this % allocation keeps changing on it's own.
I make a change somewhere else in the project and these
allocations change. This is driving me crazy - what am I
doing wrong!?
The tasks are all set up as fixed units which I thought
meant that Project would never adjust them on its own.
Ben
under it several tasks like MEETINGS, PHONE CALLS, Etc..
Each resource is assigned to these tasks at 5%, but for
some reason this % allocation keeps changing on it's own.
I make a change somewhere else in the project and these
allocations change. This is driving me crazy - what am I
doing wrong!?
The tasks are all set up as fixed units which I thought
meant that Project would never adjust them on its own.
Ben