Hi,
I am new to this EPM server. Kindly help me out for the below:
"Baselining of project to be allowed for only Admin and 1 audit manager"
"How to allow only admin and for 1 Audit Manager to baselining of projects
in Enter Project server 2007 (PWA) site?"
Kindly provide the steps to configure or any work around...
THanks,
rao
 
B

Ben Howard

Hello Rao,

You need to remove the Save Protected Baseline category permission from for
each category associated with the Project Manager group.

Then create a new group, called "Baseliners" or similiar, and associate this
group with the same categories as the PM group, and then enable the Save
Protected Baseline permission for each category.

Add your required uses to the Baseliners group.

Full details of permissions (which I recommend you read) are available at
http://technet.microsoft.com/en-us/library/cc197530.aspx
 