Allowing Users to Modify Start and Finish Dates

K

kingm12345

We would like for our project users to be able to modify the Start and Finish
dates from within the tasks panel of PWA. I have tried various fields through
Tools - Customer - Publish Fields and selecting "Let Resource Change Field".
I have also tried adjusting views with no success.
 
D

Dale Howard [MVP]

kingm12345 --

You are missing one step. After adding the Actual Start and Actual Finish
fields as Published fields in each project, you must click Collaborate -
Publish - Republish Assignments. Hope this helps.
 
K

kingm12345

Have tried that. The fields are now showing in the Time Sheet view but are
not editable.
 
D

Dale Howard [MVP]

kingm12345 --

Did you do these steps:

1. Add the Actual Start and Actual Finish fields as Published fields in
EVERY project
2. Click Collaborate - Publish - Republish Assignments in EVERY project
3. Modify the Timesheet view to include these two fields

Let us know.
 
A

amaia

I tried it and it works for me. In Publish fields the field type is task or
assignment? I have task
 