T
trpy2k
I have a 1500 line schedule that I inherited, and a few of the tasks are
demonstrating strange behavior.
Each time I update the task's % complete (say from 26% to 60%) Project
automatically changes the % complete to 100% complete and inserts the Actual
finish field.
So I scratch my head, undo the change and manually calculate the Actual
Duration, and try using that to get the % complete. Same thing, it jumps to
100%! Undo, and try it with the manually calculated remaining duration...
Yep, it happens again!
Further testing on some of these show that I can change this task to 40%
with no problem, but if I go to say 45%, the % cpl jumps it up to 100%
complete again.
On another task, I was able to change the % work complete. This
automatically changes the duration to a larger number and allows me to hit
the % complete that I actually need. In all cases, it changes the finish
date, which is not my intention at all, and skews my SV #'s.
Notes:
Using MS Prof 2007 SP 2
Task attributes:
Fixed Duration
300 ed duration
1 resource set to 100% units, changing the resource does not help.
Baselined
Help needed for this frustrating situation,
Thanks
demonstrating strange behavior.
Each time I update the task's % complete (say from 26% to 60%) Project
automatically changes the % complete to 100% complete and inserts the Actual
finish field.
So I scratch my head, undo the change and manually calculate the Actual
Duration, and try using that to get the % complete. Same thing, it jumps to
100%! Undo, and try it with the manually calculated remaining duration...
Yep, it happens again!
Further testing on some of these show that I can change this task to 40%
with no problem, but if I go to say 45%, the % cpl jumps it up to 100%
complete again.
On another task, I was able to change the % work complete. This
automatically changes the duration to a larger number and allows me to hit
the % complete that I actually need. In all cases, it changes the finish
date, which is not my intention at all, and skews my SV #'s.
Notes:
Using MS Prof 2007 SP 2
Task attributes:
Fixed Duration
300 ed duration
1 resource set to 100% units, changing the resource does not help.
Baselined
Help needed for this frustrating situation,
Thanks