A
andy
hope someone can advise,
I have several projects which run two seperate working calanders, older
version projects run at a 8 hr "day", and newer versions run at 7.4 hrs "day".
The way we work (rightly or wrongly) is to ask the resource to estimate the
duration in days how long the task will take. The resource would not be 100%
allocated over this duration.
I have been asked to change the 8hr day projects into the 7.4hr day
versions. the problem i have is that if i just use the newer calandar the day
duration length increases by 8%( the difference) as it assumes i need more
time.
Is there a simple way I can keep the same duration length.
hope this makes sense?
Regards
I have several projects which run two seperate working calanders, older
version projects run at a 8 hr "day", and newer versions run at 7.4 hrs "day".
The way we work (rightly or wrongly) is to ask the resource to estimate the
duration in days how long the task will take. The resource would not be 100%
allocated over this duration.
I have been asked to change the 8hr day projects into the 7.4hr day
versions. the problem i have is that if i just use the newer calandar the day
duration length increases by 8%( the difference) as it assumes i need more
time.
Is there a simple way I can keep the same duration length.
hope this makes sense?
Regards