B
Bill Vallance
I need to amortize the one-time and fixed costs associated with material
resources over the entire span of my project WITHOUT setting the timespan
for the associated tasks to the length of the project. An example - I need
to erect construction fencing at the start of the project. I want to show a
0 hours milestone task indicating that the fencing has been erected. But, I
want to amortize the rental cost for the fencing over 12 months. Is there a
way to amortize the cost without having a task length of 365 days?
Many Thanks,
Bill Vallance
Admirtalty Services
resources over the entire span of my project WITHOUT setting the timespan
for the associated tasks to the length of the project. An example - I need
to erect construction fencing at the start of the project. I want to show a
0 hours milestone task indicating that the fencing has been erected. But, I
want to amortize the rental cost for the fencing over 12 months. Is there a
way to amortize the cost without having a task length of 365 days?
Many Thanks,
Bill Vallance
Admirtalty Services