V
VTN
Hi,
I have an approval task that goes to a board committee. This board
committee only meets on a certain day each month. How can I schedule this
activity so that the task gets approved on the next specific day in the month
after its predecessor activity is complete? So for example, if the committee
meets ever 1st of the month, if the predecessor finished on April 15th, the
approval would take place on May 1st.
Thanks!!
I have an approval task that goes to a board committee. This board
committee only meets on a certain day each month. How can I schedule this
activity so that the task gets approved on the next specific day in the month
after its predecessor activity is complete? So for example, if the committee
meets ever 1st of the month, if the predecessor finished on April 15th, the
approval would take place on May 1st.
Thanks!!