N
neostar77
I have a task or tasks that recalculates the number of hours which I don't
want to. It means it then re-calculates the total number of project hours and
that's not what I want.
I'll give you an example of what I mean:
I set a task to 44 hrs.
I then have a % complete column at 70%. Then I change the status to 100% for
that task and it re-calculates the hours to something like 46.8 or 47.54
hours or something like that.
Also, if I add another resource, it re-calculates like that too for that
specific task.
I tried to change the task from "fixed units" to "fixed duration" but I
don't know what I'm doing with it as it re-calculates another task or two.
What am I doing wrong?
want to. It means it then re-calculates the total number of project hours and
that's not what I want.
I'll give you an example of what I mean:
I set a task to 44 hrs.
I then have a % complete column at 70%. Then I change the status to 100% for
that task and it re-calculates the hours to something like 46.8 or 47.54
hours or something like that.
Also, if I add another resource, it re-calculates like that too for that
specific task.
I tried to change the task from "fixed units" to "fixed duration" but I
don't know what I'm doing with it as it re-calculates another task or two.
What am I doing wrong?