Has anyone implemented the Portfolio Analyzer OLAP extension for Task Earned
Value? If so - Can anyone tell me why the BCWS & BCWP reported in Project
Center and within Project Professional are different than the BCWS and BCWP
reported in the Analysis Services Cube? The cube is totally up to date, but
the hours are different.
Ex: in Project A:
Portfolio Analyzer/Analysis Services: BCWS:1816, BCWP: 1528
in Project Center / MS Project Pro: BCWS: 2916, BCWP: 1426