E
El
I am trying to use the Analyze Timescale in Excel feature. The challenge I
have is the MS Project Analyze Timescale in Excel wizard spreads the time at
the subtask level and I also need the work hours spread at the summary level.
Is there an easy way to summarize the baseline information over the various
days without doing it manually in Excel. Also how does the wizard determine
how the hours are spread out across the start and finish dates. In some
cases I noticed the hours are spread out evenly. In other cases I noticed
the hours are front load (example 7 hour day and 1 hour in day two for 8 work
hors). Still on some task the hours are back loaded (1 hour in day 1 and 7
hours in day two for 8 work hours).
have is the MS Project Analyze Timescale in Excel wizard spreads the time at
the subtask level and I also need the work hours spread at the summary level.
Is there an easy way to summarize the baseline information over the various
days without doing it manually in Excel. Also how does the wizard determine
how the hours are spread out across the start and finish dates. In some
cases I noticed the hours are spread out evenly. In other cases I noticed
the hours are front load (example 7 hour day and 1 hour in day two for 8 work
hors). Still on some task the hours are back loaded (1 hour in day 1 and 7
hours in day two for 8 work hours).