Hi All,
I am using the Analyze Timescaled Data function in Project 2003 for project
reporting.
When I use this function on one of my project schedules, it us cuts off
approx. the first 4 months of data. When I tryed to do it again, I noticed
that the project start date is set to 6th August when the actual project
start date was 26th April.
Any ideas why this happens?
Thanks. Greg