Analyze Timescaled Data - Truncated

G

Greg B

Hi All,

I am using the Analyze Timescaled Data function in Project 2003 for project
reporting.

When I use this function on one of my project schedules, it us cuts off
approx. the first 4 months of data. When I tryed to do it again, I noticed
that the project start date is set to 6th August when the actual project
start date was 26th April.

Any ideas why this happens?

Thanks. Greg
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top