J
Jim Sipe
Running PS2007 with the latest patches. I have the forward capacity settings
set to 24 months. An OLAP Cube view for any resource is only showing 320
hours of Capacity with a Time Filter set for all of 2010. It would seem that
this value should be 2080 hours if the resource is 100% available. What is
happening here?
Thanks in advance
set to 24 months. An OLAP Cube view for any resource is only showing 320
hours of Capacity with a Time Filter set for all of 2010. It would seem that
this value should be 2080 hours if the resource is 100% available. What is
happening here?
Thanks in advance