Another Newbie Question

P

Paul Axelrod

The default task link is set for Finish-to-Start.
Is there a way to change this to SS or FF?
Thank you.
 
M

Mike Glen

Hi Paul,

Welcome to this Microsoft Project newsgroup :)

No - but you could set up a template. Please see FAQ Item: 8. New Project
Template. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top