Another 'Non-working time question'

  • Thread starter Matthias Jenschke
  • Start date
M

Matthias Jenschke

Hi NG,

perhaps someone can help me on this :
I am trying to create a Gantt for an extremly short project (just 2,5 days)
with a lot of short steps. The problem is, 2/3 of the diagram are taken by
the non-working time. Is there any way to hide this time ?
If I zoom out, the 2hour lasting steps are too small to spot.

Thanks for your time reading this

Matthias Jenschke
 
M

Mike Glen

Hi Matthias,

Welcome to this Microsoft Project newsgroup :)

Sorry, no :(

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 
G

Gérard Ducouret

Hello Matthias,

Sorry, this feature doesn't exist :-(

Gérard Ducouret
 