Another problem about Progress Bar

N

Newbie

Hello,
In Project Pro, the progress bars are compliant with the tracking data in
the Task Usage.
The tracking data is well displayed in the PWA Timesheets.
The progress bar is streching 3 weeks too long in the PWA page "View a
project"
Any idea ?
Thanks
 
G

Gary L. Chefetz [MVP]

newbie:

This would indicate that the task is finishing ahead of schedule and that
you're not updating the progress on the plans correctly to bring the
completed parts back to the status date. Have you ever used the tracking
function in Project to adjust the schedule after accepting task updates in
PWA? Have you looked at the tracking settings in Project?
 
N

Newbie

Hello Gary,
There is not any task finishing ahead of schedule : all the Actual Work
entries are on the left of the Status date. Most of the views displays a
progress symbol accordingly, except the PWA page "View a project" which
displays a fictive progress 3 weeks ahead.
Thansk for any hints!
 
G

Gary L. Chefetz [MVP]

I can't help you without knowing everything about the task. Type? Original
work? Assignment units? etc..
 