D
Don
I am trying to understand how Task Type works. Are there any circumstances
under which Task Type settings behave exactly the same way, regardless of how
you change a task? I set the default task type in the Tools, Options,
Schedule Tab and saved my work. Then on a set of tasks, I changed the task
type and increased and decreased the three variables-- units, work, and
duration. What happened was that as I made the changes, MS Project gave me
the same messages regardless of what I did. Maybe I don't have something set
correctly, but I can't figure out what!
under which Task Type settings behave exactly the same way, regardless of how
you change a task? I set the default task type in the Tools, Options,
Schedule Tab and saved my work. Then on a set of tasks, I changed the task
type and increased and decreased the three variables-- units, work, and
duration. What happened was that as I made the changes, MS Project gave me
the same messages regardless of what I did. Maybe I don't have something set
correctly, but I can't figure out what!