ANother question regarding dates

A

antares

Thanks Paul Linde
now clear; I was thinking that duration=finshi-start...

another question - when i change dates (project start date for example ) or
dates of some tasks..some task cells (star finish duration) in my ms project
2007 turn into blue color (are filled in blue).... what that mean ?

Thank you
 
P

Paul Linde

The light blue color indicates which cells that was affected because of your
last action. In a big project with lots of dependencies you might affect a
lot of data even if you are only making small changes.
--
Hope this helps,

Paul